SAP MM Self Test Questions

1. To view the most up to date planning data (available stock, orders, reservations, etc.) on a material, use the: (more than one answer can be correct) A Stock Overview report. B List display of material and accounting documents. C MRP list. D Stock Requirement list. E Standard Analysis for a material

2. A material forecast can be used by the following MRP types: (Only one answer is correct) A Manual Reorder point planning. B Automatic reorder point planning. C Forecast based planning.check D Time phased planning. E Storage location MRP

3. Materials planning can be set to automatically generate: (more than one answer can be correct) A Contracts. B Purchase Requisitions. C Purchase Orders. D Planned Orders. E Delivery Schedules.